Project status
Goal |
Outcome |
Improve clickthrough rate by 5% |
Goal accomplished. |
Click through rate improved by 6% |
| Ramp to 50% of users by 12/15 | Ramped to 50% by 12/21 |
| Ramp to 100% of users by 12/31 | Ramped to 100% by 12/31 |
<aside>
💡 For the following areas, think on things like: Meeting expected goals, hitting expected timelines, stress levels, communication, collaboration, accounting for edge cases ahead of time, and speeding up feedback loops.
</aside>
🙌 What went well
Allow 5 minutes for everyone to write down items. Then discuss
- Jordan: The team was able to adapt quickly to unexpected changes in project scope.
- Lisa: Technical design doc was completed quickly and we were able to start development early.
- Tom: We ramped to 100% of users on schedule.
🌱 What needs improvement
Allow 5 minutes for everyone to write down items. Then discuss
- Liz: There were instances where the project scope wasn't clearly defined which led to confusion.
- Sean: Feedback loops could have been faster - there was often a delay in addressing concerns raised by the team.
- Jordan: There were some technical issues that weren't anticipated which caused minor setbacks.
- Jordan: We weren’t able to meet our goal of 50% ramp by 12/15 due to some of the unexpected technical issues.
💡 Ideas for what to do differently
Allow 5 minutes for everyone to write down items. Then discuss